PSTA Real-Time Bus Arrival
You can find the Stop ID on the bus stop sign or in the PSTA app.
Powered by PSTA Clever Devices BusTime.
Until further notice, Beach Dr NE from 8th Ave to Coffee Pot will be blocked due to sewer work. Please catch the bus along 7th Ave between Beach Dr and Northshore Dr NE.
Start: Sep 28, 2026 6:00am
Variant B
31st St S and 5th Ave S will be blocked due to sewer line repair. Please catch the bus northbound along 28th St S and 5th Ave S.
Start: Sep 29, 2026 8:00am
End: Sep 30, 2026 5:00pm
6th Ave S between 6th St and 7th St S will be blocked due to AC installation. Please catch the bus along 6th Ave S and 6th St S.
Start: Oct 2, 2026 7:30am
End: Oct 4, 2026 5:00pm
Until further notice, Jeffords Street will be blocked due to street construction. Please catch the bus northbound along Fort Harrison Ave between Jeffords and Park Streets and southbound along Corbett Street between Druid Rd. S. and Ft. Harrison Ave.
Start: Aug 17, 2026 12:00am
Until further notice, Central Avenue and Beach Blvd to Bayshore will be blocked due to sewer work. Please catch the trolley along Central Avenue and 2nd Street to 3rd Street.
Start: Aug 16, 2026 6:00am
Until further notice, Beach Dr NE and 18th Avenue North will be blocked due to sewer work. Please catch the bus along 15th Ave between Beach Dr and NorthShore Drive N.
Start: Aug 14, 2026 10:30am
Until further notice, MLK Jr Dr & Pinellas Ave will be blocked due to road work. Please catch the bus along MLK Jr Dr & Lincoln Ave.
Start: Aug 13, 2026 9:00am
Variant B
Until further notice, MLK Jr Ave will be blocked for a road closure. Please catch the bus along MLK Jr Ave & Lakeview Rd.
Start: Jul 22, 2026 8:20am
Until further notice, 116th Ave N will be blocked due to road flooding. Please catch the bus along 110th Ave N and 4th St N.
Start: Jul 20, 2026 4:00am
Westbound
Until further notice, westbound 9th Ave N between 16th St and 22nd St will be blocked for water main break repair. Please catch the bus along 5th Ave N between 16th St N and 28th St N.
Start: Jun 22, 2026 7:30am
Until further notice, 71st Street North between 54thth Avenue North and 38th Avenue North will be blocked for paving work. Please catch the bus along 71st Street North to 38th Ave to 66th Street North to 54th Avenue North to 71st Street North.
Start: Jun 8, 2026 7:30am
Until further notice, 71st Street North between 54thth Avenue North and 38th Avenue North will be blocked for paving work. Please catch the bus along 71st Street North to 38th Avenue North to 66th Street North to 46th Avenue North.
Start: Jun 8, 2026 7:30am
Until further notice, 30th Avenue North and 28th Street North will be blocked for stormwater repair. Please catch the bus along 28th Street North and 28th Avenue North.
Start: May 16, 2026 5:00pm
The route will no longer turn at Jeffords St & Fort Harrison due to the turn being too tight. Please catch the bus along Ft. Harrison & Corbet.
Start: May 1, 2026 6:00am
The route will no longer turn at Jeffords & Myrtle due to the turn being too tight. Please catch the bus along Druid Rd at the rear of the hospital.
Start: Apr 3, 2026 6:00am
Until further notice, 28th Street at 54th Ave N will be blocked due to road construction. Please catch the bus south of 50th Ave N on 28th Street.
Start: Apr 17, 2026 12:00am
Until further notice, Pierce St and Myrtle Ave will be blocked. Please catch the bus at Park Street Terminal.
Start: Apr 14, 2026 6:00am
Until further notice, Pierce St and Myrtle Ave will be blocked. Please catch the bus at Park Street Terminal.
Start: Apr 14, 2026 6:00am
Until further notice, Pierce St and Myrtle Ave will be blocked. Please catch the bus at Park Street Terminal.
Start: Apr 14, 2026 6:00am
Until further notice, Pierce St and Myrtle Ave will be blocked. Please catch the bus at Park Street Terminal.
Start: Apr 14, 2026 6:00am
Until further notice, Park Street and 46th Avenue North will be blocked for sidewalk installation. Please catch the bus along 46th Avenue North to 66th Street North to 38th Avenue North.
Start: Apr 9, 2026 8:00am
Until further notice, 71st Street North and 54th Avenue North will be blocked for sidewalk installation. Please catch the bus along 54th Avenue North to 66th Street North to 38th Avenue North.
Start: Apr 7, 2026 4:00pm
On every 1st Friday of the month, from 1PM to 11PM, Central Avenue 2nd and 3rd Street will be blocked for First Friday St. Pete. Please catch the trolley along Central Avenue and 4th Street.
Start: Apr 3, 2026 1:00pm
On every 1st Friday of the month, from 6PM to midnight, Tarpon Avenue in Downtown Tarpon will be blocked for First Friday Tarpon Springs. Please catch the bus along Huey Ave.
Start: Apr 3, 2026 6:00pm
Stop UID #7249 is closed until further notice. Catch the bus at Stop UID #7256 at James Weldon Johnson Library (Jewel St South & 18th Avenue South), before Enoch Davis Center.
Start: Dec 22, 2025 2:00pm
Until further notice, 71st Street will be blocked. Passengers should catch the bus at the next bus stop.
Start: Nov 24, 2025 9:00am
PSTA Roof Updates
PSTA HQ Roof Project Information
The go-to spot for the PSTA Headquarters roof project! The long-awaited upgrade to the 20+ year old roof finally happened.
From June to October 2026, contractors installed a new roof system across the campus to keep our buildings safe and dry for years to come.
Project Snapshot
- Timeline: June to October 2026
- Buildings: Admin, Operations, Fuel & Revenue
- Area covered: about 60,563 square feet
- Warranty: 30 years
What is a “New Roof System”?
It’s a multi-layer roof installed right over the existing one. We didn’t have to tear off the old roof, so the buildings stayed protected from rain throughout the project.
Why didn’t we replace the whole roof?
A full replacement means stripping everything down to the roof deck. It takes longer and costs more than installing a new roof system over the existing roof. Replacement is needed when a roof is badly damaged or when there are concentrated areas of moisture.
Before construction, crews did a nuclear roof scan to check for moisture. They also cut small test openings called core samples to check the materials underneath.
The results showed that most of the roof sections were dry enough to support the new roof system. A few sections had too much moisture, so material in those sections was removed before the new roof went on.
What was the roof scan?
Crews used a specialized moisture scan on selected roof sections to look for moisture trapped below the visible surface. They also made small test openings, called core samples, to confirm the materials and conditions underneath.
The scan was not intended to measure every square foot included in the construction project. Its purpose was to identify which tested areas could remain and which areas required removal and replacement.
Check out this picture showing the results of the roof scan.

Red squares show moisture over 25%. Based on these results, material was removed from sections B, C, and E before the new roof went on.
STEP 1: ROOF BASE
The new roof system starts with crews installing new insulation and a rigid cover board. These create a stable base for the roof.
STEP 2: BASE SHEET
Next comes the first waterproof layer. It comes in large rolls. As crews unroll the material, they heat its underside with a propane torch so it bonds in place.
STEP 3: CAP SHEET
A stronger top layer called the cap sheet adds the second waterproof layer and a hard surface.
STEP 4: FINISHING & REFLECTIVE COATING
Metal finishing and a reflective coating protect the roof from sun and weather and reflect heat.

The contractor documented work on the roof and took 100+ photos. Here are a few photos from those reports to show the new roof system being installed. See the full reports (PDF).
New coverboard secured over the existing roof

The rigid, fire-resistant coverboard serves as the foundation for the new roof system.
🔩 Holy fasteners, Batman!
Each 4’x8’ coverboard is 32 square feet and requires 32 fasteners to attach it to the existing roof. That’s one fastener per square foot. With 60,563 total square feet included in the project, crews will use about 60,563 fasteners just to secure the coverboard.
Crew member using a propane torch to apply the base sheet

The torch heats the asphalt on the underside as the black membrane is slowly unrolled and bonded to the coverboard.
Crews install the base sheet across a
larger section of the roof

This view shows several stages at once, including exposed coverboard, newly applied base sheet, and rolls ready for installation.
A crew member applies cap sheet
flashing along a parapet wall

Parapets are the low walls around the roof’s edge. Extending the roofing material up these walls helps keep water from entering where the surfaces meet.
Newly installed cap sheet on the
Admin Building roof

The cap sheet adds the second waterproof layer. A reflective coating will be applied later to complete the roof surface.
Newly installed cap sheet on the Operations Building roof

This July 29 view shows the cap sheet in place.
These are a few of 100+ photos from the contractor progress reports.
Click the link below to see the full reports!
Have Questions?
- Project Inquiries: For questions regarding this project, contact Amanda Green, Project Manager II at agreen@psta.net or (727) 540-1868.
- Facilities Needs: For urgent building maintenance issues, contact the on-call Facilities line at (727) 612-2257.